The customer called and ask that Belzona provide a solution and products to rebuild the four pump bowls, Belzona recommended Belzona 1111 and 9111 by using Belzona products saved the customer time and money instead of welding the cost savings was about $6300.00 for not welding and no heat treatment was required.
Application Method
Pumps were dismantled by the CMF Millwrights and blasted and than cleaned using Belzona 9111, Belzona 1111 was mixed using the Belzona tooling and application started by using a short bristle brush to fill heavy corrosion areas and finished using a Belzona applicator.
Belzona Facts
The customer was pleased that the local Consultant provided his time to work with the apprentices to show them the techniques of the Belzona application when rebuilding this type of equipment.
Contact your nearest Belzona Consultant and schedule a free evaluation!
The secondary clarifiers at the Water Pollution Control Center were pitted and deteriorated due to chemical attack from the biological treatment process.
The centrifuge was suffering from erosion-corrosion and scale buildup. They needed a product that would protect the equipment but also help reduce the buildup and improve the efficiency of the equipment